DholeraLand Paperwork 35 steps · 8 stages · checked 4 August 2026

Step 35 of 35 · stage 8, building permission in dholera sir

Single window for a new unit

The Apex Authority (Gujarat Infrastructure Development Board) is the single point of contact for starting an economic activity or setting up a unit, amenity or infrastructure in the SIR. Approval from it precedes the offer of land by DSIRDA.

Official wording
Route a new unit or economic activity through the Apex Authority single point of contact
Stage
Stage 8, Permission to build inside Dholera SIR
Where you go
DSIRDA and the Apex Authority
Online or in person
Not stated
What it costs
No fee published
How long
The Apex Authority shall communicate its decision to the concerned person and the...
Record id
SIR-DEV-03, step 35 of 35
01

Where you go, and how

Apex Authority under the GSIR Act, 2009 - Gujarat Infrastructure Development Board (GIDB) - or the agency it specifies; DSIRDA then makes the land offer

Mode: the source does not say whether this is done online or in person

This office handles 4 of the 35 steps in the register. What else it does, and what it charges.

02

What to have with you

Not stated The government source for this step does not publish a list of documents. That absence is recorded in the register rather than filled in from an unofficial checklist, so treat any list you are handed elsewhere as somebody's practice rather than as a rule. The document lists that do exist are collected on one page.

03

The form you fill in

Proposal 'in such form containing such particulars, and in such manner and along with such fees as may by regulation prescribed by the Apex Authority' - no form number is given in the Act

04

What it costs

No fee published. This is one of the 18 steps of 35 where no government source we read publishes an amount, so nobody can tell you the figure in advance from an official page.

Here is exactly what was searched, quoted from the register's own limitations list:

Apex Authority (GIDB) single-window proposal fee under section 18(2) of the GSIR Act 2009: left to Apex Authority regulations, which were not found published. Recorded as null.

05

How long it takes

Quoted from the source, in its own words:

The Apex Authority shall communicate its decision to the concerned person and the Regional Development Authority 'as early as possible' - no fixed number of days is prescribed in the Act.

No number of days is fixed at all. The Act says the Apex Authority answers as early as possible and fixes no number of days. That is our reading of the wording printed above, which is why the wording is printed above.

The nine stated timings in the register are compared on one page.

06

What to watch out for

The register keeps a note against this step. It is the part most people find out too late, so it is printed in full rather than summarised.

FEE IS NOT FIXED IN THE ACT - it is left to Apex Authority regulations, which were not found published on the pages examined. Recorded as null. Section 19 preserves the Gujarat Special Economic Zone Act, 2004 for units inside an SEZ that falls within the SIR. Section 23 lets a person holding the minimum contiguous area prescribed by the Apex Authority apply for integrated development of that area.

07

The law behind it

Section 18, Gujarat Special Investment Region Act, 2009; section 23 for integrated development of a large area

08

Where this came from, and what comes next

Where this came from. Status OFFICIAL, no blog source used.
Citation: Gujarat Special Investment Region Act 2009, pages 18-19: s.18(1) 'The Apex Authority shall be the single point of contact for starting an economic activity or setting up a unit, amenity or infrastructure in the Special Investment Region.'
Government page: https://www.indiacode.nic.in/bitstream/123456789/6138/1/the_gujarat_special_investment_region_act,_2009.pdf
Value date: Gujarat Act No. 2 of 2009
Local file read: sir.html / pg_sir_act.html (captured dholera.gujarat.gov.in SIR ACT page)
Last verified: 4 August 2026

Found something wrong here? Send the government page that corrects it to corrections@dholera.support and the register is changed at the source, so the fix reaches every page at once.