DholeraLand Paperwork 35 steps · 8 stages · checked 4 August 2026

Step 28 of 35 · stage 6, if the developer defaults

Appeal to the RERA tribunal

Challenges an order of the Authority or the Adjudicating Officer.

Official wording
Appeal to the Gujarat Real Estate Appellate Tribunal
Stage
Stage 6, If the developer defaults
Where you go
GujRERA and the tribunal
Online or in person
Offline (demand draft prescribed)
What it costs
Rs. 1,000 (rupees one thousand) by demand draft
How long
No timing stated
Record id
RERA-03, step 28 of 35
01

Where you go, and how

Gujarat Real Estate Appellate Tribunal

Mode: Offline (demand draft prescribed)

This office handles 4 of the 35 steps in the register. What else it does, and what it charges.

02

What to have with you

The source names 3 things the office asks for. Take them all in one go and the visit is usually one visit.

  • Attested true copy of the order under challenge
  • Documents relied upon and referred to in the appeal
  • Index of the documents

Quoted from the prerequisite list in the register. Where the source names a detail rather than a document, such as a survey number, it is listed as the source words it.

03

The form you fill in

Form 'A' under Rule 3 of the Gujarat Real Estate (Regulation and Development) (Matters Relating to the Gujarat Real Estate Appellate Tribunal) Rules, 2016 (in force from 29 October 2016)

04

What it costs

Quoted from the government source, in its own words:

Rs. 1,000 (rupees one thousand) by demand draft

No part of this figure has been rounded, converted or updated by us. If the department has revised it since 4 August 2026, the correction address is in the footer. Every published fee in the register sits on one page.

05

How long it takes

No timing stated. A department that does not publish a service standard cannot be held to one, which is worth knowing before you plan around a date.

No timeline is stated for this step in any source examined for this register. Where a statute prescribes a period it is recorded; where it does not, the value is left empty rather than filled with a turnaround time from an unofficial source.

06

The law behind it

Rule 3, Gujarat Real Estate (Regulation and Development) (Matters Relating to the Gujarat Real Estate Appellate Tribunal) Rules, 2016

07

Where this came from, and what comes next

Where this came from. Status OFFICIAL, no blog source used.
Citation: https://gujrera.gujarat.gov.in/resources/staticpage/FAQs%20ADJ_26.05.2021.pdf page 37, item 4.2
Government page: https://gujrera.gujarat.gov.in/
Value date: FAQ document dated 26 May 2021
Last verified: 4 August 2026

Found something wrong here? Send the government page that corrects it to corrections@dholera.support and the register is changed at the source, so the fix reaches every page at once.