Stage 3 of 8 · 1 step
Non-agricultural permission
How do you convert agricultural land to non-agricultural use in Gujarat? One step, and it is the one that decides whether anything can be built. Section 65 of the Land Revenue Code runs a three month clock on the Collector, and the permission is deemed granted if that clock runs out. Extracted 2026-08-04 from official Gujarat sources; every record in this stage is tagged OFFICIAL.
A statutory fee is published for 1 of these 1 steps and a timeline is stated for 1. Every missing figure below is printed as a chip that links to the declared gap explaining what was searched.
Offices and portals that own these steps
- Empowered officer by area:
The steps, in order
Wide table. Scroll it sideways to reach the fee and timeline columns; the step number stays in place.
| Step no. | Step | Office or portal | Form named in the source | Statutory fee | Timeline stated | Mode | Source |
|---|---|---|---|---|---|---|---|
| 15GJ-NA-01 | Obtain Non-Agricultural (NA) permission under section 65 of the Land Revenue Code | Empowered officer by area: (A) Collector - Mahanagar Palika, Urban Area Development Authority, Notified Area... | Prescribed application at Annexure-2 to Revenue Department Resolution No. full wording | A Rs. 3-00 court fee stamp is prescribed on the application form itself. full wording | STATUTORY: section 65 requires the Collector to inform the applicant of his decision within THREE MONTHS; where he fails to do so... full wording | Online application via iORA; the 2008 resolution prescribes... | OFFICIAL Resolution dated 1 July 2008; Land Revenue Code text... |
The statutory basis named for this stage
- Section 65, Gujarat (Bombay) Land Revenue Code, 1879; Revenue Department Resolution No.
Declared gaps inside this stage
- Gap 7: NA permission: the CONVERSION TAX and NA ASSESSMENT amounts are not in Resolution NAP/1006/425/K dated 1-7-2008, which fixes only the procedure, the Rs. 3-00 court fee stamp on...