DholeraProcess Desk Rev 2026-08 · 35 steps · 8 stages · 20 gaps declared

Step 33 of 35 · record SIR-DEV-01 · stage 8

Apply to DSIRDA for development permission (Form C)

No person or entity may erect or occupy any building or structure within the Special Investment Region except with the previous permission of the Regional Development Authority. Form C is that application. This step is owned by Chief Executive Officer, Dholera Special Investment Regional Development Authority (DSIRDA), Gandhinagar. No statutory fee is published for it. A timeline is stated in the source. Source type: OFFICIAL, value date GSIR Act 2009 (Gujarat Act No. 2 of 2009); GTPUDA 1976 (President's Act No. 27 of 1976)....

33SIR-DEV-01
Record id
SIR-DEV-01
Stage
8. Dholera SIR development permission · Dholera SIR - development permission
Step number
33 of 35
Office or portal
Chief Executive Officer, Dholera Special Investment Regional Development Authority (DSIRDA), Gandhinagar
Online or offline
Offline (application to the CEO, DSIRDA)
Statutory basis
Sections 8, 15 and 16, Gujarat Special Investment Region Act, 2009; sections 27, 29, 32, 34 and 49, Gujarat Town Planning and Urban Development Act, 1976 (applied by section 17 of the GSIR Act, under which DSIRDA is the 'Appropriate Authority' for the SIR area)
Prerequisites listed
4
Source type
OFFICIAL
OFFICIAL No blog source used
Source: doc_172.pdf page 1 (form title and addressee); doc_173.pdf pages 1-19 (checklist); GSIR Act 2009 pages 17-18 (s.16(2) previous permission required, s.16(5)(a) fifteen-day appeal, s.17(3) DSIRDA is the Appropriate Authority under GTPUDA); gtpuda.pdf page 26 (s.29 three-month deemed grant) and page 27 (s.32 one-year validity, three-year aggregate cap)
Official page: https://dholera.gujarat.gov.in/form-c/40
Value date: GSIR Act 2009 (Gujarat Act No. 2 of 2009); GTPUDA 1976 (President's Act No. 27 of 1976); DSIRDA form and checklist as published on dholera.gujarat.gov.in, captured 2026-08-04
Local artefact: doc_172.pdf (Form No. C, 5 pages, from the DGDCR Appendix D, pages 230-234); doc_173.pdf (19-page DSIRDA development-permission scrutiny checklist); fc.html / sir.html (captured dholera.gujarat.gov.in navigation)

What this step achieves

No person or entity may erect or occupy any building or structure within the Special Investment Region except with the previous permission of the Regional Development Authority. Form C is that application.

The form named in the official source

Form No. C - 'Application for development permission under section 8, 15 of GSIR Act, 2009 and 27, 34 and 49 of GTPUD Act, 1976', Appendix D to the Draft General Development Control Regulations (DGDCR) of DSIRDA. Accompanied by the DSIRDA scrutiny checklist for a development permission case ('વિકાસ પરવાનગીના પ્રકરણની ચકાસણીનું પત્રક').

Statutory fee

Not stated No official fee published, gap 10

Why this is empty. DSIRDA development permission (Form C) fee and BU scrutiny fee: NOT PUBLISHED. Form No. C carries no fee clause and the BU checklist has a blank line for the scrutiny fee amount. The DSIRDA General Development Control Regulations (DP Report 2 / GDCR) at https://dholera.gujarat.gov.in/dp-report-2/35 was not among the local artifacts and may carry a fee schedule; it was not retrieved. Recorded as null.

Timeline stated in the source

Under section 29 of the Gujarat Town Planning and Urban Development Act, 1976, which applies mutatis mutandis in the SIR: if the appropriate authority fails to communicate its order to the applicant within THREE MONTHS from the date of receipt of the application, the permission shall be DEEMED TO HAVE BEEN GRANTED on the expiry of that period. Section 32: every permission granted or deemed granted under section 29 remains in force for ONE YEAR and then lapses; the authority may extend it by periods not exceeding one year at a time, subject to an aggregate maximum of THREE YEARS. Appeal against a DSIRDA decision lies to the Disputes Resolution Forum within FIFTEEN DAYS (including public holidays) of the decision, and a second appeal to the Disputes Settlement Mechanism within a further fifteen days.

Prerequisite documents

Notes recorded with this step

THE DEVELOPMENT PERMISSION FEE IS NOT PUBLISHED on the Form C page or in the form itself; recorded as null. The site's Development Permissions menu also carries 'Checklist - For DP' at /for-dp/42 and 'Checklist - For BU' at /for-bu/43, and a Professional Registration list and form at /form/46. Under GTPUDA section 49(1)(c), where a town planning scheme is in force and the appropriate authority does not communicate its decision within three months of the acknowledgment of receipt, permission is likewise deemed granted. Section 16(6) of the GSIR Act empowers DSIRDA to pull down or demolish anything built contrary to its decision and recover the cost.

Declared gaps that touch this step

How we know

Every figure above is quoted from the source named in the record slip, with its value date. Nothing on this page has been converted, rounded, averaged or carried across from another state or another year. Where the source is silent, the page says so and links to the declared gap that records what was searched.

Citation: doc_172.pdf page 1 (form title and addressee); doc_173.pdf pages 1-19 (checklist); GSIR Act 2009 pages 17-18 (s.16(2) previous permission required, s.16(5)(a) fifteen-day appeal, s.17(3) DSIRDA is the Appropriate Authority under GTPUDA); gtpuda.pdf page 26 (s.29 three-month deemed grant) and page 27 (s.32 one-year validity, three-year aggregate cap)
Value date: GSIR Act 2009 (Gujarat Act No. 2 of 2009); GTPUDA 1976 (President's Act No. 27 of 1976)...